As stated 2024-07-09: To Approve and Authorize the City Manager to Execute Task Order 2024-01 with Kimley-Horn and Associates, Inc. for Engineering Services for the South Courtenay Parkway Water Main Replacement Project…
First cited 2024-07-09 · most recently cited 2025-06-10.
Encumbrances
Each row is a meeting where money for this project was described as committed but not yet paid out — escrowed, encumbered, obligated, or under an executed contract ("base contract", "change order", "task order").
-
$169,1072024-07-09 · Council$169,107 To Approve and Authorize the City Manager to Execute Task Order 2024-01 with Kimley-Horn and Associates, Inc. for Engineering Services for the South Courtenay Parkway Water Main Replacement Project; To Approve as a Multi- Year Contract from FY2024 through FY2025; Approve a…Consent agenda item 6, approved with the Consent agendafiscal period not recorded
-
$53,4362025-06-10 · Council$53,436 To Approve Amendment 1 to Task Order 2024-01 under Continuing Services Agreement RFQ-23-12-COC with Kimley-Horn and Associates, Inc. in the amount of $53,436 for Engineering Services for the South Courtenay Parkway Water Main Replacement Project; To Approve a Resolution Amending…Consent agenda item 1, approved with the Consent agendafiscal period not recorded
Expenditures
No spending citations on this project appear in the archive yet. The committed amounts listed under Encumbrances above have not yet been reported as paid in any later meeting. As later meetings cite actual spending, those records will appear here.