Schoolhouse Street Water Main Replacement Encumbered
As stated 2017-04-11: Approve Task Order 2017-18 with Jobear Contracting, Inc. for the Schoolhouse Street Water Main Replacement, Project No. WS17SS; To Approve a Resolution Amending the Fiscal FY2017 Budget; Approve a…
First cited 2017-04-11 · most recently cited 2017-04-11.
Encumbrances
Each row is a meeting where money for this project was described as committed but not yet paid out — escrowed, encumbered, obligated, or under an executed contract ("base contract", "change order", "task order").
-
$22,9952017-04-11 · Council$22,995 Approve Task Order 2017-18 with Jobear Contracting, Inc. for the Schoolhouse Street Water Main Replacement, Project No. WS17SS; To Approve a Resolution Amending the Fiscal FY2017 Budget; Approve a Resolution Authorizing the City Manager to Approve Change Orders in an amount not…fiscal period not recorded
Expenditures
No spending citations on this project appear in the archive yet. The committed amounts listed under Encumbrances above have not yet been reported as paid in any later meeting. As later meetings cite actual spending, those records will appear here.
Numbers are sums of the dollar amounts cited in the linked meetings. They do not reconcile against the city's general ledger. Use them as navigation into the public-meeting record, not as the city's official budget figures.