SCADA Migration Project Encumbered
As stated 2025-07-22: Approval of Task Order 2025-14 with Carollo Engineers, Inc. Orlando, Florida, in the amount of $624,009.18 for the SCADA Migration Project at the Jerry Sellers Water Reclamation Facility.
First cited 2025-07-22 · most recently cited 2025-07-22.
Encumbrances
Each row is a meeting where money for this project was described as committed but not yet paid out — escrowed, encumbered, obligated, or under an executed contract ("base contract", "change order", "task order").
-
$624,0092025-07-22 · Council$624,009.18 Approval of Task Order 2025-14 with Carollo Engineers, Inc. Orlando, Florida, in the amount of $624,009.18 for the SCADA Migration Project at the Jerry Sellers Water Reclamation Facility.Consent agenda item 1, approved with the Consent agendafiscal period not recorded
Expenditures
No spending citations on this project appear in the archive yet. The committed amounts listed under Encumbrances above have not yet been reported as paid in any later meeting. As later meetings cite actual spending, those records will appear here.
Numbers are sums of the dollar amounts cited in the linked meetings. They do not reconcile against the city's general ledger. Use them as navigation into the public-meeting record, not as the city's official budget figures.