East Peachtree Street Water Main Improvement Spent

As stated 2017-04-11: Authorize a Purchase Order to be issued to Maxwell Contracting Inc. in the amount of $80,945.00 for the construction of a sidewalk, ADA compliant curb ramps, gravity wall, curbing and pedestrian…

First cited 2017-04-11 · most recently cited 2017-04-11.

Allocated (sum of citations)
—
0 citations
The allocated figure covers 0 citations, the encumbered 0 citations and the spent 1 citation, listed on this page. Not covered by the figures: amounts whose record names no project (listed on the Money page) and minutes the City has not posted.
Spent (sum of citations)
$80,945
1 citation
The spent figure covers the 1 citation classed as payments, listed under Expenditures. It does not cover citations classed as committed or allocated.

Expenditures

Each row is a meeting where this project was discussed with a dollar amount in spending language ("spent", "paid", "expended", "obligated", "contract awarded").

  • $80,945
    2017-04-11 · Council
    $80,945.00 Authorize a Purchase Order to be issued to Maxwell Contracting Inc. in the amount of $80,945.00 for the construction of a sidewalk, ADA compliant curb ramps, gravity wall, curbing and pedestrian signal upgrades on Peachtree Street at U.S.1 as part of the East Peachtree Street…
    fiscal period not recorded

Numbers are sums of the dollar amounts cited in the linked meetings. They do not reconcile against the city's general ledger. Use them as navigation into the public-meeting record, not as the city's official budget figures.